TELEHOUSE
Design and build of a datacenter in Magny-les-Hameaux
Phase 2
Work on the datacenter at the TH3 Magny-les-Hameaux Campus (78) is progressing rapidly. A datacenter to match the customer’s ambitions, as part of the Greater Paris development project.
The project involves the construction of the second 1,600 sq. metre module of the TH3 data centre for Telehouse, an ambitious project involving more than 300 people.
The Magny 2 datacenter is at the cutting edge of technology, with 2 IT rooms and an IT capacity of 3MW. With a PUE of 1.3, this data centre is designed to minimise its environmental impact.
Congratulations to the Telehouse France and Cap Ingelec teams involved in this major project. Delivery in 2025.
second module
IT rooms
IT power
P.U.E.