The Panpharma site at Luitré-Dompierre (35) draws to a close

Specialising in the manufacture and distribution of injectable medicines, PANPHARMA has decided to reconfigure its industrial site at La Selle-en-Luitré (35), built in 1983, in order to strengthen and modernise its production capacities.

CAP INGELEC is responsible for the design and implementation of part of the PMG project, including the creation of a new penicillin production unit and the reconfiguration and extension of another.

The study period ran from October to December 2022. Work will then start in January 2023, with the creation of aseptic cleanrooms and the renovation of existing cleanrooms.

The 4 main stages of the project :

  • Milestone 1: Production unit buildings – Modification of the UP2 building to integrate the new process machines – delivery October 2023
  • Milestone 2: Construction of a UPP production building (approximately 700 m² of clean rooms and two technical rooms of 700m2 each) – delivery July 2024
  • Milestone 3: Complete modification of the existing UP1 Bis production building – delivery August 2024
  • Milestone 4: Connection of the new and existing buildings and closure of the PMG project – delivery scheduled for March 2025